LCWD-2023-165 dated 06-27-24
Pipeline Installation at Brgy. Arimbay, Brgy. Kawit East
to Brgy. Cabagñan West, and Brgy. Cruzada, Legazpi City (Re-Bid)
INVITATION TO BID FOR PIPELINE INSTALLATION AT BRGY. ARIMBAY, BRGY. KAWIT EAST TO BRGY. CABAGÑAN WEST, AND BRGY. CRUZADA, LEGAZPI CITY (RE-BID)
Work Order (WO) No. & Date: 2023-09-08 dated October 2, 2023
Reference No. & Date: 11008472 dated 07-03-2024
Activities | Schedule |
1. Issuance of Bidding Documents | July 3, 2024 to July 23, 2024 |
2. Pre-bid Conference | July 11, 2024 at 1:00 PM (LCWD Admin. Services Dept. Time) |
3. Submission and receipt of Bids | On or before July 23, 2024 at 11:30 AM (LCWD Admin. Services Dept. Time) |
4. Eligibility Check and Opening of Bids | July 23, 2024 at 1:00 PM (LCWD Admin. Services Dept. Time) |
5. Bid Evaluation | July 24, 2024 at 1:00 PM (LCWD Admin. Services Dept. Time) |
6. Post-qualification | August 5, 2024 |
7. Notice of Award | Within fifteen (15) calendar days from date of receipt of the recommendation of the BAC to award the contract by the Head of the Procuring Entity (LCWD Board) or its duly authorized official.
|